Forecasting

What makes a forecast
worth acting on.

A useful forecast needs a current view of the work left, the cost already incurred and the commitments still to come. Progress-based measures also need an independent assessment of completion. The records must support the question you are asking.

Discipline, not elapsed time

A long job is not automatically a measurable one

There is a common instinct that a job becomes readable once it is far enough along. In practice it runs the other way. Time elapsed alone does not establish whether a forecast is reliable. A job early in delivery may have useful evidence; a job near completion may still have missing costs or uncertain remaining work.

Progress-based measures need assessed progress

Margin against work done, and any read on under-claiming, start here. Somebody has to look at the job and say what is built.

Progress that follows the claims measures billing

A legitimate number, and some businesses run on it. It answers a different question, and comparing it back to the claim tells you nothing new.

Progress derived from cost is circular

Completion taken from cost spent against cost forecast returns the forecast margin by construction. That circular comparison cannot independently establish margin movement.

Inputs

What a forecast needs that a budget row does not give you

The position — recorded, committed, claimed — comes straight off the job. A forecast also needs the remaining work and any unrecorded incurred cost. Comparing it with the original margin needs a frozen baseline. A missing input blocks only the measure that depends on it.

Remaining uncommitted work

What is left that nobody has ordered or scheduled, reviewed by a person. This is the input that makes a forecast a forecast.

Anything accrued and not yet recorded

Cost incurred that has not reached the ledger. Counted once, and never twice when it is already sitting inside a commitment.

A frozen baseline

What the job was approved at, versioned. This is required to measure movement from the original margin; a current forecast can still be assessed on its own inputs.

Each cost appears exactly once. Remaining labour belongs in the forecast even though labour never passes through committed cost. A credit must not reduce the same exposure twice. Payment timing is a cash question and never a margin.

Status

Four statuses that explain what you can use

Every measure carries its own status, so a gap in one place does not quietly degrade everything else.

Ready

Inputs complete and compatible. The figure reconciles to the records named beside it.

Provisional

Computed, but resting on something assumed, stale or partial. Shown as provisional, and never added into a ready total.

Needs input

Blocked, with the missing input named, the conclusion it prevents, and who can supply it.

Not applicable

It does not apply to this scope. Said plainly, rather than shown as a zero.

Every aggregate also shows its coverage — how much of the job is included and what was left out. A ready subset is never presented as the whole picture, and a ready forecast is a checked forecast rather than a promise about the outcome.